Tres Rios
Home
Wetlands Project Info
-   Schedule
-   River Restoration
Wetlands Research
Photos
Frequently Asked Questions
Birders
Links
Contact Us

Schedule

Construction of the Tres Rios Full Scale Project levees and emergent wetlands has been completed. Refer to the schedule below for the individual phases and their start and completion dates.

Schedule:

Phase
Tentative Start
Tentative End
1A (levee 105th to Avondale Blvd.)
---------------
Completed 5/2007
1B (levee Avondale Blvd. to the Agua Fria River)
---------------
Completed 6/2008
2A (Effluent Pump Station)
7/2009
7/2012
2B (Emergent/Flow Regulating Wetlands)
-----------------
Completed 12/2010
3A-3B (Riparian and open water in river)
7/2010
7/2012
3C (El Mirage to Agua Fria River)
Unfunded
---------
4 Recreational Elements
8/2012
7/2013


Last modified on 02/28/2012 09:05:09